Norris Farm House

Here are pictures of our new house taken as it was being built by Tony and Guy Boils in 2003.
Tony and Guy did an excellent job for us. They began work on April 8th and finished their part of the construction on September 15th. They were easy to work with, listened to our requests, built our house the way we wanted it built and were extremely polite. Their crew exhibited the same politeness and desire to please as the Boils. I have nothing but good things to say for their construction of our home.

Thanks to Tony and Guy Boils!


 
 
MVC-057F
   I'm laying out the house location for the bulldozer driver to start dozing.
MVC-077F
   The driveway is roughed in place.
MVC-078F
   The foundation has been poured and cement blocks are almost completed.
MVC-079F
   The location of the garage is on the front side of the house.
MVC-080F
   A higher view from behind the house.
MVC-081F
   The view from the south end of the house.
MVC-082F
   The back porch is closest to the camera.
MVC-083F
   The rain stopped work for a couple of days.
MVC-084F
   The gravel makes the walking a little easier, now if it will ever dry out.
MVC-085
   I enlisted some help to cut down a tree so the power company would string the lines.
MVC-086F
   L to R - Ray, Sabra, Pauline, Brent, Linda and Jim are working while I'm taking a picture.
MVC-087F
   Right about now is when Pauline's jacket was ate up by the mulcher.
MVC-091F
   After the tree was down, Tri-County Electric set the pole.
MVC-092F
   They are almost ready to hook up the temporary power.
MVC-091F
   The crew used air nailers on the floor decking.
MVC-093F
   It made fast work of getting the floor nailed on the joists.
MVC-092F
   Tony (in the straw hat) is laying out the lines for the walls.
MVC-094F
   They are snapping a line for the end wall.
MVC-095F
   They're snapping lines for the bedrooms and hallway.
MVC-108F
   The first walls are up and more are ready to go up.
MVC-109F
   The kitchen walls were built out of straight lumber they picked out of the delivery.
MVC-111F
   The crew is working on the front walls after window and door headers have been added.
MVC-112F
   The walls are done and ceiling joists are being added to the porch.
MVC-113F
   The stack of orange lumber is the OSB for the exterior walls.
MVC-115F
   They're adding more framing above the pantry.
MVC-116F
   A view of the framing from the road.
MVC-122F
   Tony and Guy are laying flooring in the bonus room, while the crew is working on siding with OSB.
MVC-123F
   Guy helping Tony lock in a piece of floor decking.
MVC-125F
   The crew nailing up OSB for the exterior walls.
MVC-130F
   Cumberland County Water digging to find the main water line.
MVC-131F
   They found it, made the connection and then knocked it loose.
MVC-132F
   Most of the roof joists have been cut and nailed in place.
MVC-133F
   Now we are realizing how the house is going to set on the location.
MVC-134F
   Bracing is in, and scaffolds have been set for upstairs work.
MVC-135F
   Another set of scaffolds were used for work on bracing the roof joists.
MVC-136F
   The side walls are in and collar ties are being placed for the bonus room ceiling.
MVC-138F
   The bracing of the roof joists is almost completed.
MVC-137F (Altered, Rotation)
   The window in the front of the bonus room has been framed.
MVC-140F
   Temporary braces for the back porch roof are in place.
MVC-141F
   Tyvek has been added to wrap the house and the gable has been framed.
MVC-143F
   The house is almost ready for the roof decking to begin.
MVC-144F
   All the OSB for the exterior walls has been added and one row of roof decking is on the bonus room.
MVC-145F
   Wall sheating and Tyvek has been added to the gable end walls.
MVC-146F
   The bonus room has the roof decking on so the main rafters can be tied in to the roof of the bonus room.
MVC-147F
   The gable end has been covered with OSB.
MVC-148F
   The roof decking is on the bonus room and a prow has been added.
MVC-149F
   The front bedroom has the gable completed.
MVC-165F
   More roof decking is being added.
MVC-167F
   The crew is using a nail gun for the roof decking and a crow bar to remove the boards they used for standing on. They only used a nail gun for the floor and roof decking.
MVC-170F
   It's getting close to time for a roof.
MVC-172F
   This is one of the shingles we picked for the roof.
MVC-174F
   Here are the color choices for the siding, we chose the GRAY color on the bottom.
MVC-177F
   The roof decking is done, waiting on the roofing crew to begin.
MVC-178F
   The last of the walls were put between the roof above the half bath and the roof above the dinning area.
MVC-181F
   The crew is using the tractor and tossing trash out of the window into the scoop.
MVC-182F
   The chimney for our stove has been added and facia boards.
MVC-183F
   The roofers have arrived and started on the garage. This was taken after about 2 hours of work.
MVC-184F
   The last square goes on the garage roof.
MVC-185F
   They used the tractor to lift the shingles to the roof.
MVC-188F
   A couple of two man crews and the shingle carrier put on the entire roof.
MVC-189F
   It's almost lunch time when I took this picture.
MVC-191F
   After lunch more shingling.
MVC-192F
   The end of one day's work had the house over half done.
MVC-193F (Altered, Rotation)
   The fiberglass columns have been set for the back porch.
MVC-194F
   There is also a fiberglass column in the entrance area inside.
MVC-197F
   Looking from one end of the bonus room towards the highway.
MVC-198F
   The roof cap is being put on the bonus room and the rest of the roofers are working on the front side.
MVC-199F
   The Anderson back doors for the living room are installed.
MVC-200F
   The roofers are almost done, 53 squares in less than 2 days.
MVC-202F
   They ran out of shingles with just a little left to do.
MVC-203F
   Probably one more bundle would have finished the job.
MVC-204F
   The front door has been installed.
MVC-205F (Altered, Rotation)
   The bath tub and shower enclosure has been set in place.
MVC-206F (Altered, Rotation)
   The entry way to our house from the inside.
MVC-207F (Altered, Rotation)
   The whirlpool tub is set in it's location and the Anderson window is in place also.
MVC-208F (Altered, Rotation)
   The shower is in the master bath.
MVC-209F
   The floor is clean after Linda, Stacey and I picked up the scrap pieces. I saved them for kindling for our stove.
MVC-210F (Altered, Rotation)
   Looking at the leaded glass in our front door from inside.
MVC-211F
   I'm looking forward to filling the tub and turning on the whirlpool.
MVC-212F
   The electric meter box has been mounted.
MVC-215F
   The circuit breaker box inside the garage is also in place.
MVC-216F (Altered, Rotation)
   CAT5 cable has been run by Brent and I for the computer networking.
MVC-218F (Altered, Rotation)
   The PC center is located in the study. We also ran over 200 feet of coaxial cable for TV.
MVC-219F
   The roof is completed, junk picked up and ready for cement and brick work.
MVC-221F
   The bricks around the foundation blocks are being laid.
MVC-222F
   More brick work under the half bath window has been done.
MVC-223F
   Jerry's brick work corners are nice.
MVC-224F
   Landslide!
MVC-226F
   The concrete has been poured in the garage for the floor.
MVC-229F
   They have bull floated the concrete and will wait for it to harden a little before trowling it smooth.
MVC-230F
   Brick work around the front porch showing the columns too.
MVC-240F
   Part of the HVAC unit is sitting on the garage floor.
MVC-241F
   The electrical panel is being wired while the heating contractor has installed metal ductwork.
MVC-242F
   The brick work will go completely around the house.
MVC-244F
   I talked to Guy and they put the bricks across the back porch too.
MVC-243F
   Once the brick work was done, the same crew did the aluminum and vinyl for the over hang.
MVC-246F
   Boxing in the overhang with metal.
MVC-247F
   The vinyl siding is going up while they are boxing in the overhang. They only have to put the scaffolds up one time when they do it at the same time.
MVC-248F
   The front garage wall is completed
MVC-250F
   They left a hole for our outside spotlights.
MVC-252F
   Finishing the top of the front garage / bonus room wall.
MVC-253F
   They're spraying in the insulation. It fills all the cracks and voids that way.
MVC-254F (rotated)
   They spray it on really thick and let it build up.
MVC-257F (Rotation)
   The second guy uses a power rubber roller to scrape off the extra right down to the 2 by 4s. The extra is picked up and run through again.
MVC-266F
   The front side of the house is starting to look finished.
MVC-268F
   The siding is only done on the front side.
MVC-269F
   A picture from the hay field across the creek.
MVC-272F
   The drywall crew started work in the garage.
MVC-273F
   They put up 12 foot long boards.
MVC-275F
   The 4 guys put up 230 sheets in about 1-1/2 days.
MVC-277F
   After we picked up the mess it was looking more like the inside of a house.
MVC-278F
   Now we can tell how big our rooms are going to be.
MVC-279F
   Looking out of 3 of the 4 windows in the front bedroom.
MVC-280F
   The master bedroom looking towards the bath.
MVC-282F
   The cement truck is pouring the concrete out of a chute for the back porch.
MVC-283F
   You can still see the steel rebar they have laid for the floor of the porch.
MVC-284F
   Guy is grading the side yard and covering up some drywall pieces.
MVC-285F
   They're raking the back porch concrete while the other guys are directing the pour.
MVC-286F
   I never expected them to get the truck that close to the house, but that's almost the last of the concrete coming out now.
MVC-287F
   Two of the crew are floating the concrete with a smaller float.
MVC-289F
   They're trowling it smooth, then they will broom it to give it a little roughness for traction.
MVC-292F
   They're striking lines across the concrete.
MVC-293F
   Jerry and his helper are siding the back side of the bonus room.
MVC-310F
   A picture from the road.
MVC-311F
   A straight on shot.
MVC-312F (Altered, Rotation)
   Part of the front porch railing has been installed.
MVC-313F
   The fiberglass columns have been set for the step railings.
MVC-315F (Altered, Rotation)
   The back porch concrete is hard and I have installed our porch swing.
MVC-316F
   The drywall has been taped and mudded, the screws have been covered too.
MVC-317F
   Showing the dinning and entry way after mudding.
MVC-318F
   The guys are painting on the texture on the ceiling in the bonus room.
MVC-319F
   First they put on a heavy coat of plaster.
MVC-320F
   Then they go over that coat with a roller that has reliefs cut in it and that makes the raised places and the texture on the ceilings.
MVC-323F
   Jerry is cutting the last piece of vinyl for the chimney.
MVC-325F
   Jerry is installing the last piece of vinyl for the chimney.
MVC-332F
   The guys are forming and cutting aluminum seamless guttering and downspouts.
MVC-334F
   They're now installing the downspout.
MVC-336F
   The outside is almost done, but we do need a garage door.
MVC-337F
   The stainless steel chimney cap is on.
MVC-340F
   Stacey and the Purple color she picked for her bedroom.
MVC-343F
   I'm pointing to the green color Linda picked for our bedroom.
MVC-344F
   The front bedroom is a bright yellow.
MVC-345F
   Tan is the best description for the living room color.
MVC-346F
   Stained trim is going up in the living room area.
MVC-348F
   The doors have been painted and hung.
MVC-349F
   The closet doors are hanging in the front bedroom.
MVC-351F
   The stained doors and trim for the study has been added.
MVC-352F
   The mahogany wood of our front door took stain well. We still need locks and hardware.
MVC-355F
   The dinning area will have a two tone paint theme divided by a chair rail.
MVC-356F
   The rear doors have been stained also.
MVC-359F
   The inside column has been painted.
MVC-360F
   The trench for the electrical line is being dug and pipe is ready to put in with a rope inside for the power company to pull their wires.
MVC-361F
   This is showing the trench for future reference.
MVC-362F
   Johnny is digging the trench right to the electrical box.
MVC-363F
   Everyone should have one of those tools, it makes it so easy, Johnny doesn't even have to ride on it.
MVC-364F
   The mortar for the tile work, I needed another bag, so I sent this picture to Linda for her to see what to buy.
MVC-366F
   I've been digging trenches to bury the black pipe that will take the water from the guttering away from the house.
MVC-367F
   I put 300 feet of black pipe into the ground to take the water most of the way down the hill.
MVC-369F
   The garage door has been installed.
MVC-370F
   They put in a garage door and opener from the Over Head Garage Door company.
MVC-373F
   Brent and I tiled the utility room.
MVC-376F
   Two half doors leading to our bath room have been hung.
MVC-379F
   I laid the tile in the small bathroom.
MVC-384F
   The shutters around the windows makes the house look like it is almost done on the outside.
MVC-385F
   Guy added shutters around our bathroom windows so it would match the front side windows.
MVC-386F
   The handrail for the steps has been installed .
MVC-387F
   The electrical fixtures and ceiling fans are going up.
MVC-388F
   Ceiling fans in all the bedrooms have been installed.
MVC-389F
   Our lights in the master bathroom are in place.
MVC-390F
   Two sconce lights are working in the dinning area and the chair rail has been added.
MVC-391F
   The outside lights at our front door are working.
MVC-392F
   The master bath tile floor is going down.
MVC-394F
   These guys are cutting tile for the tub surround.
MVC-396F
   The results of their work looks good to me.
MVC-398F
   They are digging a curtain drain above where our laterals will be placed.
MVC-399F
   The HVAC crew is setting the Bryant heat pump outside unit and wiring it.
MVC-405F
   They dug a 200 foot curtain drain to keep water from running down the hillside and filling our laterals.
MVC-408F
   Roll roofing is placed under the hardwood floor as it is being nailed down.
MVC-409F
   Two installers working on the floor in different areas makes the work go faster.
MVC-404F
   Our floor finish is called Gunstock. It is pre-finished 3/4" oak hardwood.
MVC-410F
   The flooring went smoothly and quickly too, a day and a half for the hardwood in the house.
MVC-414F
   Gravel for our laterals has been dumped.
MVC-415F
   The dirt is still damp from covering the hole for our septic tank.
MVC-416F
   I'll use this picture to find the septic tank if I ever need to dig it up.
MVC-417F
   This shows the three boxes for the laterals to branch off the main line.
MVC-418F
   350 feet of laterals set level is not an easy job in KY.
MVC-420F
   I hope this will remind me where the laterals are located if I ever need to know.
MVC-421F
   We finally picked out a light for the study and I installed it.
MVC-422F
   I finished the tile work for under the wood stove.
MVC-423F
   I finished the tile work in the half bath.
MVC-426F
   The lights are on, but nobody's home...yet!
MVC-427F
   I'm trying to run our first light bill up.
MVC-428F
   The whirlpool works. Ask me about it sometime.
MVC-430F
   The kitchen cabinets are going in a little at a time.
MVC-431F
   The sink cabinets are installed.
MVC-432F
   The vanity in the little bathroom with a solid surface counter has been set.
MVC-434F
   We made a change on these cabinets. We added glass doors that haven't been put on.
MVC-436F
   Our new appliances have arrived and been installed.
MVC-438F
   Looking towards the sink and stove with the counter tops installed too. We have made coffee and some canned soup!
MVC-439F
   I really like the wood panel they placed under our breakfast bar.
MVC-441F
   I have installed the stove and Chi Chi is enjoying his first fire in it.
MVC-449F
   The carpet has been installed as the last item to be finished.
MVC-446F
   Linda has started decorating and the contractors are done with their work.

 


[Gallery] [Title Page] [Links] [About]